The lowest construction quotation can leave the owner with the highest unfinished obligation

Prices become comparable only when scope, allowances and responsibilities are reconciled. Owners should assess the total commitment required to deliver an accepted result.

Sint Maarten; Caribbean

Khalil K. Revan · Managing Director, IAWA Technical Consultants B.V.

A quotation is a price for a particular understanding of the work. When that understanding differs between contractors, the totals answer different questions.

One price may include access equipment, protection and waste removal. Another may assume that the owner provides them. One may allow for making good adjacent finishes; another may stop at the boundary of the principal task. The apparent saving can therefore be a transfer of responsibility rather than a reduction in cost.

The owner's objective should be to establish the total commitment needed for an accepted result. That requires a common scope, a clear account of uncertainty and an assessment of whether the proposed delivery arrangement is credible.

Give every bidder the same problem to solve

The scope should identify the intended result and the information on which the contractor is expected to price. Relevant drawings, measurements, condition findings and operating restrictions should be consistent across the enquiry.

Where design or investigation remains incomplete, state that position. A contractor cannot reliably price a defined solution to an undefined technical problem. Appropriate professional input may be required before the owner can compare the proposed options.

Ask bidders to identify the work included, the quantities or pricing basis, material assumptions and exclusions. This gives the comparison a structure and helps reveal where apparently similar offers differ.

A site visit can improve understanding, but it should not become a substitute for recording the agreed scope. Material clarifications need to be shared consistently so that later prices are compared on the same basis.

Adjust the comparison using evidence

Assume, as an illustration, that quotation A is $40,000 and excludes access equipment and waste removal. Quotation B is $46,000 and includes both. If comparable written prices for A's exclusions total $8,000, A's adjusted comparison is $48,000.

The arithmetic is simple. The important qualification is that the additional prices must address the same requirement and be realistically obtainable. An owner's rough allowance should be labelled as an allowance, rather than presented as a confirmed price.

The adjusted total also does not settle the appointment. Technical suitability, programme, supervision, relevant capability and the terms of the offer still require assessment.

The comparison should identify provisional sums and other allowances separately. Explain what they cover, how they will be adjusted and who bears the consequence if the actual requirement differs. A low allowance can make a quotation appear competitive while leaving significant expenditure unresolved.

GAO's cost-estimating guidance is a useful methodological reference for documenting scope and assumptions. At the scale of a property project, the same discipline helps an owner understand why one total differs from another.

Test the route from appointment to completion

A proposed start date may depend on a deposit, material availability, owner selections or access that has not been agreed. Confirm those dependencies before treating the date as a commitment.

The programme should include procurement and the conditions required to work productively. For an occupied property, access, deliveries, noise and protection arrangements need to reflect the actual operation. An attractive duration can lose its meaning if it assumes unrestricted working in a building that must remain in use.

Ask how supervision and specialist input will be provided. The answer should be specific to the assignment. General statements about capability are less useful than a clear account of the proposed team, responsibilities and availability.

Completion criteria should also be agreed at appointment. The owner needs to know what inspections, tests, records and defect resolution are required before the work is accepted. Payment milestones should be reconciled with identifiable deliverables and the actual contractual terms.

Resolve uncertainty before it becomes a variation

Unforeseen conditions and owner changes can occur. The control is to distinguish them from omissions or assumptions that could have been clarified before appointment.

Keep a record of the agreed starting scope. When a change is proposed, require a description, reason, price and programme effect, together with the authorised decision. The process should be practical enough for the size of the work while retaining a dependable record.

The preferred contractor should have an opportunity to reconcile the comparison and explain material differences. That conversation can expose a misunderstanding before it becomes a dispute.

Owners should also consider their own obligations. Delayed selections, unavailable access or unconfirmed instructions can affect the contractor's ability to deliver. A credible appointment identifies those responsibilities rather than assuming all delivery risk sits with one party.

The strongest purchasing decision is one the owner can explain after the project is complete: the scope was understood, the prices were compared fairly, the uncertainties were visible and the selected team had a workable route to the required result. That is a better defence of value than the fact that one total was initially the lowest.

Discuss the implications

IAWA can help develop a common scope and a clear quotation comparison before the owner commits to the work.

References

Related IAWA service

Construction and renovation

Explore the service scope →

Khalil K. Revan is Managing Director of IAWA Technical Consultants B.V., Sint Maarten.

Discuss your question